Ten years of project inspection/resident engineer and special inspection experience on the San Diego Clean Water Program a $1.5 billion Capital Improvement Program to upgrade and build new wastewater treatment plants, outfalls, pump stations, trunk and interceptor sewer pipelines. Projects included

  • New Sedimentation tanks and restoration of Sedimentation tanks
  • New Digesters and restoration upgrades of existing digesters
  • Digester gas mixing systems, piping and gas compressors.
  • Central boiler facilities
  • Power Co-generation upgrade
  • Operations and control buildings
  • Sludge pump-station
  • Chemical feed systems
  • Odor control systems
  • Headwork's bar-screens and concrete restoration
  • Grit removal pump and piping upgrades
  • Force main isolation structures
  • Process piping installation
  • Rehabilitation of on-shore outfall
  • Pump station No. 1 & 2 upgrades
Point Loma Wastewater Treatment Plant

Point Loma Wastewater Treatment Plant

Point Loma wastewater treatment plant sedimentation tanks restoration and odor removal systems upgrade

Point Loma wastewater treatment plant sedimentation tanks restoration and odor removal systems upgrade

Two new sedimentation tanks 11&12 including new odor control systems

Two new sedimentation tanks 11&12 including new odor control systems

Construction of new digester No 8 tank floor

Construction of new digester No 8 tank floor

Digesters 7 & 8 and new excess gas flares at top right

Digesters 7 & 8 and new excess gas flares at top right

New sludge pumping station

New sludge pumping station

Cogeneration facility with two 2.3 megawatt (total 4.6) V12 engine generators

Cogeneration facility with two 2.3 megawatt (total 4.6) V12 engine generators

Pump Station 2 installation of ultrasonic flow meter spools for eight 50,000 GPM pumps

Pump Station 2 installation of ultrasonic flow meter spools for eight 50,000 GPM pumps